![]() WHAT: Concrete delivery (5-6 trucks) for installation at the Service and Inspection Building Wheel Truing Pit Walls (approximately 50 cubic yards). This will include a 36 Meter Pump Truck.
WHEN: Monday between the hours of 8:00 a.m. to 11:00 a.m. HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. ----------------------------------------------------------------------------------------
WHAT: Concrete delivery (5-6 trucks) for installation at the Service and Inspection
Building Footings (approximately 50 cubic yards). This will include a 36 Meter Pump Truck. WHEN: Monday around 9:00 a.m. and 10:00 a.m., and Wednesday - Friday between the hours of 7:00 a.m. to 11:00 a.m. HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. ----------------------------------------------------------------------------------------
WHAT: Concrete delivery (5-6 trucks) for installation at the Transportation and Police
Building Footings (approximately 50 cubic yards). WHEN: Tuesday between the hours of 7:00 a.m. to 11:00 a.m. HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. ----------------------------------------------------------------------------------------
WHAT: Concrete delivery (30-35 trucks) for installation at the Service and Inspection
Building Wheel Truing Pit Upper Slab (approximately 300 cubic yards). This will include a 39 Meter Pump Truck. WHEN: Thursday and Friday between the hours of 7:00 a.m .to 11:00 a.m. HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. <><><><><>
|