Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for May 22 - 26

May 19,  2017
 
CONTACT:  Marcia McAllister
             T: 703-572-0506
             C: 571-730-9117
 
Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for May 22-26
 
The following construction deliveries are scheduled for May 22-26 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (15-20 trucks) of ballast material at the layup yard.

WHEN: Monday - Friday between the hours of 7:00 a.m. to 5:00 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (23 trucks) for installation at the Maintenance of Way building high mezzanine slab on Metal Deck, including a 38z pump truck.
 
WHEN: Thursday-Friday between the hours of 1:00 a.m. to 12:00 p.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
-----------------------------------------------------------------------------------------
 
WHAT: Precast Panel Delivery (10-12 Trucks) in 45 minute increments for installation at the Service and Inspection Building. 
 
WHEN: Monday - Friday between the hours of 7:00 a.m. to 2:00 p.m. 
 
HOW: Trucks will travel from Winchester VA, East on rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Turnout delivery (2-3 trucks) for installation in the yard lead track. 
 
WHEN: Monday (2 trucks), Wednesday (3 trucks), and Friday (2 trucks) between the hours of 7:00 a.m. to 12:00 p.m. 
 
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Concrete Ties delivery (4 trucks) for installation in the yard lead track. 
 
WHEN: Monday - Friday between the hours of 7:00 a.m. to 12:00 p.m.  
 
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
WHAT: Structural Steel Delivery (1-3 Trucks) for installation in the Warehouse Building and Service and Inspection Building. 
 
WHEN: Monday (3 trucks) and Friday (1 truck) between the hours of 6:00 a.m. - 12:00 p.m. 
 
HOW: Trucks will be coming from Tennessee, traveling North on Old Ox Rd/Rt. 606 from US 50. 
-------------------------------------------------------------------------------------------
 
WHAT: Roofing delivery (10 trucks) to be installed at the Service and Inspection Building. 
 
WHEN: Monday-Wednesday between the hours of 7:00 a.m. to 5:00p.m. Trucks will be staged off site, to allow the trucks to arrive one at a time. 
 
HOW: Trucks will travel from Carlisle, PA, South on 15, East on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.