Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for May 8 -12

May 5, 2017
 
CONTACT:  Marcia McAllister
             T: 703-572-0506
             C: 571-730-9117
 
Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for May 8 - 12
 
The following construction deliveries are scheduled for May 8 - 12 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (10-15 trucks) of ballast material at the layup yard.

WHEN: Monday - Friday between the hours of 7:00 a.m. to 5:00 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.  
-----------------------------------------------------------------------------------------
WHAT: Precast Panel Delivery (10 Trucks) in 45 minute increments for installation at the Service and Inspection Building.
 
WHEN: Monday - Friday  between the hours of 7:00 a.m. to 2:00 p.m.
 
HOW:  Trucks will travel from Winchester VA, East on Rt. 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite.
 
-------------------------------------------------------------------------------------------
WHAT: Turnout delivery (3-4 trucks) for installation in the yard lead track.
 
WHEN: Monday - Tuesday between the hours of 7:00 a.m. to 12:00 p.m.
 
HOW:   Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. 
 
-------------------------------------------------------------------------------------------
WHEN: Restraining Rail delivery (2 trucks) to be installed in the yard lead track.
 
WHEN:  Monday - Tuesday between the hours of 7:00 a.m. to 5:00 p.m.
 
HOW:  Trucks will travel from Allentown, PA, South on 15, East on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.  
 
---------------------------------------------------------------------------------------------
 
WHAT: Switch ties delivery (4 trucks) for installation in the yard lead track.
 
WHEN: Monday - Tuesday between the hours of 7:00 a.m. to 12:00 p.m.
 
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. 
 
----------------------------------------------------------------------------------------------
 
WHAT: Rebar delivery (1 truck) for installation in the Maintenance of Way Building and Transportation and Police Building Layup Yard.
 
WHEN: Monday - Tuesday between the hours of 10:00 a.m. to 12:00 p.m.
 
HOW: Trucks will travel from the Trowbridge plant along Old Ox Rd/Rt. 606 to the project site.
 
-----------------------------------------------------------------------------------------------
 
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.