August 1, 2016
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
|
Concrete Deliveries Scheduled for August 1 - August 5
The following construction deliveries are scheduled for Monday, August 1 through Friday, August 5 in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
CONCRETE DELIVERIES
![]() WHAT: Concrete delivery (30 trucks/day) and concrete pump truck for installation of Austin Sand Filter walls and foundations
WHEN: Monday, August 1, 2016 between the hours of 4:00 a.m. and 11:00 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site
WHAT: Concrete delivery (7-10 trucks/day) and concrete pump truck for installation of Service and Inspection Building hoist pit walls
WHEN: Tuesday, August 2 - Friday, August 5, 2016, between the hours of 7:30 a.m. and 1:00 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site
WHAT: Concrete delivery (7-10 trucks/day) and concrete pump truck for installation of Austin Sand Filter walls
WHEN: Friday, August 5, 2016 between the hours of 5:30 a.m. and 11:00 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.
|