Concrete Delivery Schedule for Dec. 18 - 23
 
The following construction deliveries are scheduled for Dec. 18 - 23 (Monday - Saturday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (15 trucks) of ballast material at the layup yard.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Rte 606/Old Ox Rd to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Bumping Post (2 trucks) for installation at the layup yard. 
 
WHEN: Wednesday - Friday between the hours of 7 a.m. to 5 p.m.  
 
HOW: Trucks will travel from Pennsylvania, south on I-95 and west on 267. 
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (6 trucks) for installation in the Track.
 
WHEN: Wednesday - Thursday between the hours of 9 a.m. to 12 p.m.  
 
HOW: Trucks will travel from the Titan batch plant along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (33 trucks) for installation in the Service and Inspection Building Slab on Grade including a 38z truck.
 
WHEN: Thursday between the hours of 4 a.m. to 1 p.m.  
 
HOW: Trucks will travel from the Titan batch plant along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (7 trucks) for installation in the TPSS 21A including a 36m truck.
 
WHEN: Wednesday between the hours of 7 a.m. to 12 p.m.  
 
HOW: Trucks will travel from the Titan batch plant along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (26 trucks) for installation in the Warehouse Building Slab on Grade including a 47m truck.
 
WHEN: Tuesday between the hours of 4 a.m. to 11 a.m.  
 
HOW: Trucks will travel from the Titan batch plant along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (36 trucks) for installation in the Maintenance of Way Building Slab on Grade including a 47m truck.
 
WHEN: Monday between the hours of 3 a.m. to 1 p.m.  
 
HOW: Trucks will travel from the Titan batch plant along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.