Skip to main content
Silver Line on Track

Concrete Delivery Schedule for July 3 - 7

June 30,  2017
 
CONTACT:     Marcia McAllister
      T: 703-572-0506
               C: 571-730-9117
               Marcia.McAllister@dullesmetro.com
 
Concrete Delivery Schedule for July 3 - 7
 
The following construction deliveries are scheduled for July 3 - 7 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (20 trucks) of ballast material at the layup yard.
 
WHEN: Wednesday - Friday between the hours of 7 a.m. to 5 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (20 trucks) for installation at the Transportation & Police Building Deck, including a Z Boom pump truck.
 
WHEN: Friday between the hours of 2 a.m. to 8 a.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
----------------------------------------------------------------------------------------- 
 
WHAT: Precast Panel delivery (4 trucks) in 45 minute increments for installation at the Maintenance of Way Building.
 
WHEN: Monday and Wednesday between the hours of 7 a.m. to 2 p.m. 
 
HOW: Trucks will travel from Winchester VA, East on Rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Precast Panel delivery (8 trucks) in 45 minute increments for installation at the Maintenance of Way Building.
 
WHEN: Thursday between the hours of 7 a.m. to 2 p.m. 
 
HOW: Trucks will travel from Winchester VA, East on Rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Rail delivery (1 80' truck) to be installed in the Maintenance of Way Track.
 
WHEN: Friday between the hours of 7 a.m. to 5 p.m.  
 
HOW: Trucks will travel from Allentown, PA,  South on 15, East on 267, South  on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Turnout delivery (2-4 trucks) for installation in the yard lead track.
 
WHEN: Thursday (4) and Friday (2) between the hours of 7 a.m. - 12 p.m. 
 
HOW: Trucks will  travel from Reading, PA, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
WHAT: Hollow Metal Frames delivery (1 truck) for installation in the Service and Inspection Building.
 
WHEN: Wednesday between the hours of 7 a.m. - 12 p.m. 
 
HOW: Trucks will  travel from Easton, PA, East on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
WHAT: Rebar delivery (1 truck) for installation in the Service and Inspection Building.
 
WHEN: Monday and Wednesday between the hours of 6 a.m. - 10 a.m. 
 
HOW: Trucks will  travel from the Trowbridge plant, West on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
WHAT: Temping Machine and Crane (1 truck) for work on track.
 
WHEN: Wednesday between the hours of 6 a.m. - 10 a.m. 
 
HOW: Trucks will  travel from New Jersey, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.