Concrete Delivery Schedule for Sept. 18 - 22
 
The following construction deliveries are scheduled for Sept. 18 - 22 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (20 trucks) of ballast material at the layup yard.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Rte 606/Old Ox Rd to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Precast Panel delivery (15 trucks) in 45 minute increments for installation at building TBD.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 3 p.m.  
 
HOW: Trucks will  travel from Winchester, VA, East on Rte 7, South on 28, and West along Rte 606/Old Ox Rd to the project site, making the U-turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (15 trucks) for installation in the Maintenance of Way Track including a 47m pump truck. 
 
WHEN: Tuesday and Wednesday between the hours of 4 a.m. to 10 a.m.  
 
HOW: Trucks will  travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (5 trucks) for installation in the TCR/TWF Footing.
 
WHEN: Wednesday, Thursday and Friday between the hours of 7 a.m. to 10 a.m.  
 
HOW: Trucks will  travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Turntable delivery (1 truck) for installation in the Service and Inspection Building.
 
WHEN: Monday and Tuesday between the hours of 6 a.m. to 11 a.m.  
 
HOW: Trucks will  travel from Connecticut, East on Rte 7, South on 28, and West along Rte 606/Old Ox Rd to the project site, making the U-turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
 
WHAT: Restraining Rail delivery (1 truck) to be installed in the yard lead track.
 
WHEN: Wednesday between the hours of 7 a.m. to 1 p.m.  
 
HOW: Trucks will  travel from Allentown, PA, South on 15, East on 267, South on Rte 606/Old Ox Rd and will have to turn around at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
<><><><><> 
 