Daily Traffic Reminder for Friday, April 21

April 21, 2017
 
CONTACT:      Marcia McAllister
                      T: 703-572-0506
                      C: 571-730-9117
                      marcia.mcallister@dullesmetro.com
 
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
Lane Closures and Detours Tonight on the Dulles International Airport Access Highway, Dulles Greenway and Airport Roads - Friday, April 21
 
Nighttime construction activities will take place Friday, April 21, causing lane closures and detours on the Dulles International Airport Access Highway, Dulles Greenway and airport roads.
Drivers are asked to use caution, remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions.
See below for more detailed information.  All work is weather permitting.
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Friday, April 21, 7 p.m. to 5 a.m.
What:    Left lane closed at 7 p.m. Full Closures begins at 10 p.m.; follow detour. Road reopens at 5 a.m.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Aerial guideway construction
 
{"gmap":{"map":{"options":{"center":"(38.9570502830709, -77.44591143228149)","zoom":15},"size":"full"}},"marker":{"marker0":{"position":"(38.95550432333387, -77.4464464187622)"},"marker1":{"position":"(38.961644588153575, -77.44288444519043)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
 
When:   Friday, April 21, 6 p.m. to 10 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 3.0 (from Saarinen Circle to 4/10 mile past the Centreville Road bridge)
Why:     Construction entrance acceleration/deceleration lane
 
{"gmap":{"map":{"options":{"center":"(38.953971674819684, -77.39970233537292)","zoom":16},"size":"full"}},"marker":{"marker0":{"position":"(38.95557106820309, -77.44648933410645)"},"marker1":{"position":"(38.954052606876054, -77.39445447921753)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Friday, April 21, 10 p.m. to 5 a.m.
What:    Full closure
Where:  From mile marker 0.3 to Saarinen Circle (from 2/10 mile past the Rudder Road overpass to Saarinen Circle near Garage 1), traffic will be diverted around work area.
Why:    Aerial guideway construction
 
{"gmap":{"map":{"options":{"center":"(38.958451881545514, -77.44481709100342)","zoom":15},"size":"full"}},"marker":{"marker0":{"position":"(38.95550432333387, -77.44653224945068)"},"marker1":{"position":"(38.961644588153575, -77.44305610656738)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
 
Aviation Drive/Cargo Drive
 
When:   Friday, April 21, 6 p.m. to 5 a.m.
What:    Left and center lanes closed
Where:  From 300 feet west of Autopilot Drive to Copilot Way (along the transition from westbound Aviation Drive to southbound Cargo Drive)
Why:     Duct bank work
 
{"gmap":{"map":{"options":{"center":"(38.95619512752748, -77.4518927583847)","zoom":17},"size":"full"}},"marker":{"marker0":{"position":"(38.9580072129072, -77.45262622833252)"},"marker1":{"position":"(38.95532077461942, -77.45299100875854)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
 
Package Court East and West
 
When:   Friday, April 21, 6 p.m. to 5 a.m.
What:    Closed
Where:  From Air Freight Lane to the Cargo 5 circulator road.  Follow detour through Cargo 5 parking lot.
Why:     Duct bank work
 
{"gmap":{"map":{"options":{"center":"(38.96185147695434, -77.45188202954864)","zoom":17},"size":"full"}},"marker":{"marker0":{"position":"(38.96178640863556, -77.45246529579163)"},"marker1":{"position":"(38.96178640863556, -77.44989037513733)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
 
Dulles Greenway East
 
When:   Friday, April 21, 8 p.m. to 5 a.m.
What:    Left and center lane closures
Where:  From mile marker 10 to 12.0 (from the Loudoun County Parkway overpass to 4/10 mile before the mainline toll plaza)
Why:     Striping
 
{"gmap":{"map":{"options":{"center":"(38.99727681196198, -77.47553374864196)","zoom":16},"size":"full"}},"marker":{"marker0":{"position":"(38.97909471774654, -77.45136022567749)"},"marker1":{"position":"(38.99712422503177, -77.47783899307251)"}},"circle":{},"polygon":{},"polyline":{},"rectangle":{}}
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2 construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.