DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
Lane Closures and Detours Tonight on the Dulles Greenway and Airport Roads - Thursday, June 15
Nighttime construction activities will take place on Thursday, June 15, causing lane closures and detours on the Dulles International Airport Access Highway, Dulles Greenway and airport roads.
See below for more detailed information. All work is weather permitting.
Drivers are asked to use caution, remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions.
Dulles International Airport Access Highway (DIAAH) East
When: Thursday, June 15 - Friday, June 16, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
Saturday, June 17, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What: Left lane closures
Where: From mile marker 4.7 to 5.3 (5/10 mile before to 1/10 mile past the Reston Parkway overpass)
Why: Civil work
Dulles International Airport Access Highway (DIAAH) West
When: Thursday, June 15 - Friday, June 16, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Saturday, June 17, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What: Left lane closure
Where: From mile marker 5.5 to 4.7 (3/10 before to 5/10 mile after the Reston Parkway overpass)
Why: Civil work
Autopilot Drive North and South
When: Thursday, June 15 - Friday, June 16, 9 p.m. to 5 a.m.
What: Right lane closed
Where: Between Rudder Road and Materials Road
Why: Storm pipe installation and aerial guideway construction
Dulles Greenway East
When: Thursday, June 15 - Saturday, June 17, 8 p.m. to 5 a.m.
What: Two left lanes closed
Where: From mile marker 10.0 to 12.0 (from the Loudoun County Parkway overpass to 4/10 mile before the mainline toll plaza)
Why: Aerial guideway construction
Sunrise Valley Drive East and West
When: Thursday, June 15 - Friday, June 16, 10 p.m. to 5 a.m.
Friday, June 16, 11 p.m. to 8 a.m.
What: Flagging operation
Where: At the intersection of Sunrise Valley Drive and Roark Drive, into the Herndon-Monroe Park and Ride facility
Why: Utility work
<><><><><>
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2 construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|