Important Lane and Ramp Closures for the
Week of April 30 - May 6
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening and striping, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane, shoulder, road and ramp closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway and Dulles Airport roads during the week of April 30 - May 6, 2017.
 
See below for more detailed information.  All work is weather permitting.
 
Drivers are asked to use caution remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions.
 
<><><> 
Dulles Toll Road East
 
When:   Monday, May 1 - Friday, May 5, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
Saturday, May 6, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.2 (from 1/10 mile past the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
Dulles Toll Road West
 
When:   Monday, May 1 - Friday, May 5, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
Saturday, May 6, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (from approximately 2/10 mile after the Wiehle Avenue overpass to 3/10 mile before the Route 28 overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, May 1 - Friday, May 5, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
Saturday, May 6, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From Saarinen Circle to mile marker 5.7 (5/10 mile past the Reston Parkway overpass)
Why:     Civil work
 
When:   Monday, May 1 - Saturday, May 6, 10 p.m. to 5 a.m.
What:    Full closure begins at 10 p.m.; follow detour. Road reopens at 5 a.m.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Aerial guideway construction
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, May 1 - Friday, May 5, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Saturday, May 6, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 200 feet past the ramp to Copilot Way on Saarinen Circle (from 5/10 mile before the Reston Parkway overpass to 6/10 mile past the Rudder Road overpass)
Why:     Civil work
 
When:   Monday, May 1 - Saturday, May 6, 10 p.m. to 5 a.m.
What:    Full closure
Where:  From mile marker 0.3 to Saarinen Circle (from 2/10 mile past the Rudder Road overpass to Saarinen Circle near Garage 1), traffic will be diverted around work area.
Why:    Aerial guideway construction
 
Aviation Drive/Cargo Drive
 
When:   Monday, May 1 - Saturday, May 6, 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures
Where:  From 300 feet west of Autopilot Drive to Copilot Way (along the transition from westbound Aviation Drive to southbound Cargo Drive)
Why:     Duct bank work
 
Package Court East and West
 
When:   Monday, May 1 - Saturday, May 6, 6 p.m. to 5 a.m.
What:    Closed
Where: From Air Freight Lane to the Cargo 5 circulator road.  Follow detour through Cargo 5 parking lot.
Why:     Duct bank work
 
Rudder Road West
 
When:   Monday, May 1 - Saturday, May 6, 6 p.m. to 5 a.m.
            Saturday, April 29, 10 p.m. to 5 a.m.
What:    Right lane closed
Where:  From the ramp to the Green Lot to the Blue Lot access road
Why:     Duct bank work
 
Dulles Greenway East
 
When:   Monday, May 1 - Friday, May 5, 10 a.m. to 6 pm.
            Saturday, May 6, 6 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Monday, May 1 - Saturday, May 6, 8 p.m. to 5 a.m.
What:    Two right lanes closed OR two left lanes closed
Where:  From mile marker 11.0 to 12.0 (from the Old Ox Road overpass to 4/10 mile before the mainline toll plaza)
Why:     Aerial guideway construction
 
Dulles Greenway West
 
When:   Monday, May 1 - Friday, May 5, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m.
            Saturday, May 6, 6 a.m. to midnight
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile past the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Monday, May 1 - Sunday, May 7, 12 a.m. to 12 a.m.8 p.m. to 5 a.m.
What:    Right shoulder closed continuously
Where:  From mile marker 11.2 to 11.1 (from 1/10 mile before the Old Ox Road overpass to the Old Ox Road overpass)
Why:     Sign installation
 
Sunrise Valley Drive West
 
When:   Monday, May 1 - Thursday, May 4, 9:30 a.m. to 3 p.m.
            Friday, May 5, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Thunder Chase Drive to 200 feet past Hitchcock Drive
Why:     Clearing/excavation
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.