Important Lane and Ramp Closures for the Week of Aug. 27 - Sept. 2

August 25, 2017
 
 
CONTACT: Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
 
Important Lane and Ramp Closures for the
Week of Aug. 27 - Sept. 2
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening and striping, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane, shoulder, road and ramp closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Dulles Airport roads, and surrounding roads during the week of Aug. 27 - Sept. 2.
 
See below for more detailed information.  All work is weather permitting.
 
Drivers are asked to use caution remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
 
<><><> 
 
Dulles Toll Road East
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
             Friday, Sept. 1, 10 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.2 (from 1/10 mile past the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 10 p.m. to 5 a.m.
What:    Alternating double right and double left lane closures
Where:  From mile marker 3.7 to 5.0 (from 3/10 mile past the Monroe Street/Van Buren Street overpass to 2/10 mile before the Reston Parkway overpass)
Why:     Utility work
 
Dulles Toll Road West
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
             Friday, Sept. 1, 9:30 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (from approximately 2/10 mile after the Wiehle Avenue overpass to 3/10 mile before the Route 28 overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
             Friday, Sept. 1, 8:30 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  From Saarinen Circle to mile marker 5.7 (5/10 mile past the Reston Parkway overpass)
Why:     Civil work
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 7 p.m. to 5 a.m.
What:    Two left lanes closed
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass).
Why:     Aerial guideway construction
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
             Friday, Sept. 1, 7:30 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 200 feet past the ramp to Copilot Way on Saarinen Circle (from 5/10 mile before the Reston Parkway overpass to 6/10 mile past the Rudder Road overpass)
Why:     Civil work
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 7 p.m. to 5 a.m.
What:    Two left lanes closed
Where:  From mile marker 0.4 (near the Rudder Road overpass) to Saarinen Circle
Why:     Aerial guideway construction
 
Air Freight Lane North
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 9 a.m. to 2 p.m.
What:    Northbound lane closed
Where:  From the south end of Air Freight Lane to Package Court.  Traffic will be flagged for safety.
Why:     Concrete pours
 
Aviation Drive East and West/Cargo Drive North and South
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 6 p.m. to 5 a.m.
What:    Right lane closed
Where:  From 300 feet west of Autopilot Drive to 300 feet south of the Cargo Drive/Aviation Drive transition
Why:     Concrete pours
 
Dulles Greenway East
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 10 a.m. to 6 pm. and 6 p.m. to 5 a.m.
             Friday, Sept. 1, 10 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 8 p.m. to 5 a.m.
What:    Two right lanes closed or two left lanes closed
Where:  From mile marker 10.0 to 12.0 (from 2/10 mile past the Loudoun County Parkway overpass to 4/10 mile before the mainline toll plaza)
Why:     Aerial guideway construction
 
Dulles Greenway West
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m.
             Friday, Sept. 1, 6 a.m. to noon
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile past the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Civil work
 
Sunrise Valley Drive East
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 10 p.m. to 5 a.m.
What:    Right lane closed
Where:  From Roark Drive to Thunderchase Drive
Why:     Utility work
 
Sunrise Valley Drive West
 
When:   Monday, Aug. 28 - Thursday, Aug. 31, 9:30 a.m. to 3:30 and 10 p.m. to 5 a.m.
             Friday, Sept. 1, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Thunder Chase Drive to 200 feet past Hitchcock Drive
Why:     Utility work
 
Sunrise Valley Drive East and West
 
When:   Monday, Aug. 28, 9 p.m. to 5 a.m.
             Tuesday, Aug. 29, 9 p.m. to 5 a.m.
What:    Flagging operation
Where:  Alternating lane closures at the intersection of Roark Drive and Sunrise Valley Drive
Why:     Utility work
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.