Dulles Corridor Metrorail Project crews continue construction activities for the Metrorail Silver Line Phase 2 that require lane, shoulder, and road closures and detours at locations along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Autopilot Drive, Herndon Parkway, Edmund Halley Drive, Sunrise Valley Drive, Sunset Hills Road, Lockridge Road, and Moran Road during the week of Dec. 3 - Dec. 8, 2018. In addition, there will be lane closures near the Phase 1 alignment as listed below.
 
See below for more specific dates, times and details and remember that all work is weather permitting.
 
PLEASE USE CAUTION and remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
 
<><><> 
Dulles Toll Road East
 
When:   Monday, Dec. 3 to Friday, Dec. 7, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
             Saturday, Dec. 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.2 (from just west of the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
Dulles Toll Road West
 
When:   Monday, Dec. 3 to Friday, Dec. 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
Saturday, Dec. 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (between the Route 28 and Reston Parkway overpasses)
Why:     Civil work
 
When:   Monday, Dec. 3 to Friday, Dec. 7, 9:30 a.m. - 3 p.m.
What:    Ramp Closure  
Where:  Mile marker 3.3, to Access Road
Why:     Striping
 
Dulles International Airport Access Highway (DIAAH) East

When:   Monday, Dec. 3 to Friday, Dec. 7, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
Saturday, Dec. 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 5.7 (from the Aviation Drive overpass to 5/10 mile after the Reston Parkway overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, Dec. 3 to Friday, Dec. 7, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
             Saturday, Dec. 8, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 7.3 to 0.0 (from approximately 7/10 mile west of Hunter Mill Road to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal)
Why:     Civil and Dulles Airport Metrorail Station work will be taking place within the closures
 
When:   Tuesday, Dec. 4 to Friday, Dec. 7, 10 a.m. to 2 p.m.
What:    Double left lane closure
Where:  From mile marker 0.3 to Saarinen Circle
Why: OH #1 sign removal and replacement
 
When:   Friday, Dec. 7, 9 p.m. to 7 a.m.
Saturday, Dec. 8, 7 p.m. to 5 a.m.
What:    Triple right lane closure with 20 minute stoppages
Where:  From mile marker 0.3 to Saarinen Circle
Why: OH #1 sign removal and replacement 
 
Autopilot Drive North/South
 
When:  Monday, Dec. 3 to Friday, Dec. 7, 10 a.m. to 2 p.m.
            Saturday, Dec. 8, 8 a.m. to 2 p.m.
What: Alternating left and right lane closures of varying lengths
Where: From Rudder Road to Materials Road
Why: Civil Work
 
Dulles Greenway East
 
When:   Monday, Dec. 3 - Friday, Dec. 7, 10 a.m. to 6 p.m.
Saturday, Dec. 8, 6 a.m. to 6 p.m.
What:    Alternating left and right lane closures of varying lengths
Where:  From mile marker 7.6 to 14.0 (from approximately 2/10 mile west of Waxpool Road to Route 28 overpass)
Why:     Civil work
 
When:   Monday, Dec. 3 - Saturday, Dec. 8, 10 a.m. to 8 p.m.
What:    Double left and right lane closures of various lengths
Where:  From mile marker 8.5 to 12.2 ( From Ashburn Village Blvd overpass to the main toll plaza)
Why:     RPM Install
 
Dulles Greenway West
 
When:   Monday, Dec. 3 - Friday, Dec. 7, 6 a.m. to 3 p.m.
Saturday , Dec. 8, 6 a.m. to 6 p.m.
What:    Alternating left and right lane closures of varying lengths
Where:  From mile marker 12.2 to 7.6 (from approximately 3/10 mile west of the Main Toll Plaza to Broadlands Boulevard overpass)
Why:     Civil work
 
When:   Monday, Dec. 3 to Friday, Dec. 7, 7 a.m. to 2:45 p.m.
             Saturday, Dec. 8, 7 a.m. to 2:45 p.m.
What:    Double left and right lane closures of varying lengths
Where:  From mile marker 12.2 to 10.5 (from the Ariane Way overpass to Broad Run Bridge)
Why: RPM Install
 
Sunset Hills Road East 
 
When: Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
            Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What:    Alternating right and left lane closures
Where:  From 400 feet west of Town Center Pkwy to Bechtel Building Entrance
Why:     Civil work
 
Herndon Parkway East
 
When:   Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where: From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why:     Equipment mobilization
 
Sunrise Valley Drive West
 
When:   Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Dulles Technology Drive to Dulles Station Blvd
Why: Civil Work
 
When:   Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Thunder Chase Drive to Millburn Lane
Why: Civil Work
 
When:   Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Reston Pkwy to 200' West of Edmund Halley Dr.
Why: Civil Work
 
Edmund Halley Drive North and South
 
When:   Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
             Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What:    Right shoulder closed
Where:  From Sunrise Valley Drive to 1000 feet north of Sunrise Valley Drive
Why:     Civil utility work
 
Moran Road South
 
When: Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
            Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What:    Alternating left and right lane closures
Where:  From Moran Road to Old Ox Road
Why:     Civil work
 
Lockridge Road North/South
 
When: Monday, Dec. 3 to Thursday, Dec. 6, 9:30 a.m. to 3:30 p.m.
           Friday, Dec. 7, 9:30 a.m. to 12 p.m.
What: Flagging
Where: From Moran Road to Prentice Drive
Why: Utility Crossings
 
Route 7 East
  
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Left and right lane closures
Where:  From Route 267 ramp to Spring Hill Road
Why:     Installing pipe liner
 
Route 7 West
  
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Left and right lane closures
Where:  From Chain Bridge Road to Route 267 ramp
Why:     Installing pipe repair bands and spot repairs
 
Route 123 East
  
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Left lane or right lane closure
Where:  From Old Meadow Road to Colshire Drive
Why:     Installing pipe repair bands and spot repairs
 
Route 123 West
  
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Left lane or right lane closure
Where:  From Colshire Drive to Old Meadow Road
Why:     Installing pipe repair bands and spot repairs
 
I-66 East
 
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Inside left lane and shoulder closure on a four-lane road
Where:  From Route 267 (Dulles Connector Road) north ramp to Williamsburg Boulevard
Why:     Installing pipe repair bands and liners
 
I-66 West
 
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Inside left lane and shoulder closure on a four-lane road
Where:  From Williamsburg Boulevard to Route 267 (Dulles Connector Road) north ramp
Why:     Installing pipe repair bands and liners
 
Dulles Connector Road East
 
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Alternating left lane and shoulder closures
Where:  From Chain Bridge Road to I-66
Why:     Cleaning and storm drain work 
 
Dulles Connector Road West
 
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Alternating left lane and shoulder closures
Where:  From I-66 to Chain Bridge Road
Why:     Cleaning and storm drain work
 
Spring Hill Road North
 
When:   Sunday, Dec. 2 - Friday, Dec. 7, 9:30 p.m. - 5 a.m.
What:    Right turn lane closure
Where:  From Spring Hill Road to Route 7
Why:     Installing pipe repair bands and liners
 
<><><><><>
 