Important Lane and Ramp Closures for the
Week of Feb. 4 - Feb. 10
 
Dulles Corridor Metrorail Project crews are continuing construction activities for the Metrorail Silver Line, Phase 2. Lane, shoulder, road, and ramp closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Sunrise Valley Drive, Sunset Hills Road, Moran Road, Old Ox Road, and Herndon Parkway during the week of Feb. 4 - Feb. 10. See below for more detailed information. In addition, Silver Line Phase 1 lane closures are planned during the week along the Dulles Connector Road.
 
Heavy construction work that requires the use of a large crane will be taking place at Innovation, Herndon, and Reston Metrorail Stations. The crane must be positioned on the eastbound DIAAH which will cause frequent weeknight full closures of portions of the highway. Work will take place at only one station each night and the locations of the closures will vary depending upon where the station work is taking place. The detours will entail diverting eastbound DIAAH traffic onto the eastbound DTR, then returning it to the DIAAH beyond the location of the construction activity. Notifications specific to each closure will be issued in advance of the work.
 
All work is weather permitting.
 
Drivers are asked to use caution remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.     
 
<><><> 
 
Dulles Toll Road East
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
             Saturday, Feb. 10, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.2 (from 1/10 mile past the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
Dulles Toll Road West
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
             Saturday, Feb. 10, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (from approximately 2/10 mile after the Wiehle Avenue overpass to 3/10 mile before the Route 28 overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Friday, Feb. 2 -Monday, Feb. 5, 9:30 p.m. to 5 a.m.
What:    Full closure of a section of the eastbound DIAAH
Where:  From milemarker 01.7 to 2.2 (Between the Route 28 and Centreville Road overpasses) 
Detour: Eastbound DIAAH traffic will be detoured onto the left lane of the eastbound Dulles Toll Road and then returned to the eastbound DIAAH beyond the construction activity. No toll will be charged to airport traffic. This detour will remain in place throughout the weekend.
Why:     Innovation/Herndon/Reston Station construction
 
When:   Monday, Feb. 5 - Monday, Feb. 12, 9:30 p.m. to 5 a.m.
What:    Full closure of a section of the eastbound DIAAH
Where:  From milemarker 2.7 to 4.0 (Centreville Road and Fairfax County Parkway overpasses)
Detour: Eastbound DIAAH traffic will be detoured onto the left lane of the eastbound Dulles Toll Road and then returned to the eastbound DIAAH beyond the construction activity. No toll will be charged to airport traffic. The detour will be removed each night and the road will be restored operation no later than 5 a.m. each day.
Why:     Innovation/Herndon/Reston Station construction
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
Saturday, Feb. 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From Saarinen Circle to mile marker 5.7 (5/10 mile after the Reston Parkway overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m
Saturday, Feb. 10, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 200 feet past the ramp to Copilot Way, including ramps (between the Rudder Road overpass and Saarinen Circle at Dulles Airport
Why:     Civil work and construction for Dulles Metrorail Station
 
Dulles Connector Road West
 
When:   Tuesday, Feb. 6, and Wednesday, Feb. 7, 9 a.m. to 2:30 p.m.
What:    Close left lane
Where: From 1,000 feet before the Idylwood Road overpass to 1,000 feet after the Idylwood Road overpass
Why:     Survey points along the left shoulder
 
Dulles Connector Road East
 
When:   Tuesday, Feb. 6, and Wednesday, Feb. 7, 10:30 a.m. to 3:30 p.m.
What:    Close left lane
Where: From the Chain Bridge Road overpass to the Idylwood Road overpass
Why:     Survey points along the left shoulder
 
Dulles Greenway East
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 10 a.m. to 6 p.m.
Saturday, Feb. 10, 6 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Lane closures will be between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur.
Why:     Civil work
 
Dulles Greenway West
 
When:   Monday, Feb. 5 - Friday, Feb. 9, 6 a.m. to 3 p.m.
Saturday, Feb.10, 6 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Lane closures will begin approximately 3/10 mile west of the Main Toll Plaza and end near the Broadlands Boulevard overpass
Why:     Civil work
 
Moran Road/Lockridge Road North and South
 
When:   Monday, Feb. 5 - Thursday, Feb. 8, 9:30 a.m. to 3:30 p.m.
             Friday, Feb. 9, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Old Ox Road to 1500 feet north of Lockridge/Moran Road intersection
Why:     Civil work
 
Herndon Parkway East
 
When:   Monday, Feb. 5 - Thursday, Feb. 8, 9:30 a.m. to 3:30 p.m.
             Friday, Feb. 9, 9:30 a.m. to noon
What:    Right lane closed
Where:  From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why:     Civil work
 
Old Ox Road East and West
 
When:   Monday, Feb. 5 - Thursday, Feb. 8, 9:30 a.m. to 3:30 p.m.
             Friday, Feb. 9, 9:30 a.m. to noon
What:    Right lane closed
Where:  From the 500 feet east of Moran Road to 500 feet west of Moran Road
Why:     Civil work
 
Sunrise Valley Drive West
 
When:   Monday, Feb. 5 - Thursday, Feb. 8, 9:30 a.m. to 3:30 p.m.
             Friday, Feb. 9, 9:30 a.m. to noon
What:    Right lane closed
Where:  From 1000 feet east of Edmund Halley Drive to Edmund Halley Drive
Why:     Civil work
 
Sunset Hills Road East
 
When:   Monday, Feb. 5 - Thursday, Feb. 8, 9:30 a.m. to 3:30 p.m.
             Friday, Feb. 9, 9:30 a.m. to noon
What:    Right lane closed
Where:  From 400 feet west of Town Center Parkway to 600 feet east of Town Center Parkway
Why:     Civil work
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.