Important Lane and Ramp Closures for the Week of June 14 – June 20
 
Dulles Corridor Metrorail Project crews continue construction activities for the Metrorail Silver Line Phase 2 that require lane, shoulder, and road closures and detours at locations along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Autopilot Drive, Herndon Parkway, Edmund Halley Drive, Sunrise Valley Drive, Sunset Hills Road, and Moran Road during the week of June 14 - June 20, 2020. In addition, there will be lane closures along the Phase 1 alignment as listed below.
 
See below for more specific dates, times and details and remember that all work is weather permitting. PLEASE USE CAUTION and remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
 
<><><>
 
Dulles Toll Road East
When:  Sunday, June 14 to Saturday, June 20, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where: From mile marker 1.3 to 5.2 (from just west of the Route 28 overpass to the Reston Parkway overpass)
Why:    Civil work
 
Dulles Toll Road West
When:  Monday, June 15 to Friday, June 19, 9 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
           Saturday, June 20, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where: From mile marker 5.7 to 1.5 (between the Route 28 and Reston Parkway overpasses)
Why:    Civil work
 
Dulles International Airport Access Highway (DIAAH) East
When:  Monday, June 15 to Friday, June 19, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
           Saturday, June 20 to Sunday, June 14, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where: From mile marker 0.0 to 8.0 (from the Aviation Drive overpass to Hunter Mill Road)
Why:    Civil work
 
Dulles International Airport Access Highway (DIAAH) West
When:  Monday, June 15 to Friday, June 19, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
           Saturday, June 20 to Sunday, June 14, 5 a.m. to 2 p.m. 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where: From mile marker 7.3 to 0.0 (from approximately 7/10 mile west of Hunter Mill Road to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal)
Why:    Civil and Dulles Airport Metrorail Station work will be taking place within the closures
 
Autopilot Drive North
When:  Sunday, June 14 to Saturday, June 20, 9 a.m to 2 p.m.
What:  Alternating single right or left lane closures
Where: From Rudder Road to Materials Road
Why:    Civil Work
 
Dulles Greenway East
When:  Monday, June 15 to Friday, June 19, 10 a.m. to 6 p.m. and Saturday, June 20, 6 a.m. to 6 p.m.
What:  Alternating left and right lane closures of varying lengths
Where: From mile marker 7.6 to 14.0 (from approximately 2/10 mile west of Waxpool Road to the Dulles Toll Road)
Why:    Civil work
 
When:  Monday, June 15 to Friday, June 19, 5 a.m. to 6 p.m.
What:  Left shoulder closures of varying lengths
Where: From mile marker 10.8 to 11.8 (from the Old Ox Rd overpass to a half mile before the main toll plaza)
Why:    Track Wall Repairs
 
Dulles Greenway West
When:  Monday, June 15 to Friday, June 19, 6 a.m. to 3 p.m. and Saturday, June 20, 6 a.m. to 6 p.m.
What:  Alternating left and right lane closures of varying lengths
Where: From mile marker 12.2 to 7.6 (from the Moran Road exit to Broadlands Boulevard overpass)
Why:    Civil work
 
Herndon Parkway East
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 2 p.m.
What:   Right lane closed
Where: From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why:    Material Delivery
 
Sunrise Valley Drive East and West
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 2 p.m.
What:   Right lane closed
Where: From Dulles Technology Drive to Dulles Station Blvd
Why:    Civil Work
 
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m. and 10 p.m. to 4 a.m.
Friday, June 19, 9:30 a.m. to 12 p.m. and 11 p.m. to 5 a.m.
Saturday, June 20, 7 a.m. to 3:30 p.m. and 11 p.m. to 5 a.m.
What:  Right lane closed
Where: From Thunder Chase Drive to Colts Brook Drive
Why:    Civil Work
 
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 2 p.m.
What:   Right lane closed
Where: From Reston Pkwy to 200’ West of Edmund Halley Dr.
Why:    Civil Work
 
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 2 p.m.
What:   Right turn lane & Right lane closed
Where: Intersection of Sunrise Valley Drive and Reston Parkway
Why:    Civil Work
 
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 2 p.m.
What:   Right lane closed
Where: Fairfax County Parkway
Why:    Civil work
 
Sunset Hills Road East
When: Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m. and 10 p.m. to 5 a.m.
Friday, June 19, 9:30 a.m. to 12 p.m. and 10 p.m. to 5 a.m.
Saturday, June 20, 7 a.m. to 3:30 p.m. and 10 p.m. to 5 a.m.
What:  Alternating right and left lane closures
Where: From 400 feet west of Town Center Pkwy to Bechtel Building Entrance
Why:    Civil work
 
Edmund Halley Drive North and South
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 12 p.m. and Saturday, June 20, 7 a.m. to 3:30 p.m.
What:  Right shoulder closed
Where: From Sunrise Valley Drive to 1000 feet north of Sunrise Valley Drive
Why:    Civil utility work
 
Moran Road North and South
When:  Monday, June 15 to Saturday, June 20, 7 a.m. to 5:30 p.m.
What:  Alternating left and right lane closures
Where: From Moran Road to Old Ox Road
Why:    Civil work
 
Old Ox Road East and West
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m. and 10 p.m. to 4 a.m.
Friday, June 19, 9:30 a.m. to 12 p.m.
What:  Right lane closure
Where: From 1000’ east of Old Ox Road bridge to 1000’ west of bridge
Why:    Fence installation
 
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.
Friday, June 19, 9:30 a.m. to 12 p.m.
What:  Left lane closure
Where: From 1000’ east of Old Ox Road Bridge to the Dulles Greenway NB On-Ramp
Why:    Curb repairs
 
PHASE 1 CLOSURES
 
Dulles Connector Road West
When: Monday, June 15, through Thursday, June 18, 8 a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Left shoulder closure
Where: From West Falls Church Metro Station exit ramp to bus ramp of West Falls Church Metro Station 
Why:   Seed and sod installation
 
Route 123 South
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m. 
What:  Right turn lane closure
Where:  From 100 feet past Route 267 eastbound exit ramp to Scotts Crossing Road
Why:   Underdrain installation
 
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m. 
What:  Right turn lane closure
Where:  From 100 feet past Scotts Crossing Road to Capital One Drive
Why:   Underdrain installation
 
Route 7 East
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Left turn lane closure
Where: From 300 feet before Westwood Center Drive to Route 7
Why: Manhole and sidewalk repairs
 
Route 7 West
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What: Left lane closure
Where: From 300 feet before Westpark Road to 400 feet after Westpark Road
Why:  Underdrain Installation
 
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From 300 feet before Tyco Road to 300 feet Dulles Toll Road exit ramp
Why:  Manhole and sidewalk repairs
 
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From 600 feet before Spring Hill Road to 300 feet after Spring Hill Road
Why:  Manhole and sidewalk repairs
 
Spring Hill Road South
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Right lane closure
Where: From 500 feet before Route 7 to Route 7 
Why:  Manhole and sidewalk repairs
 
Spring Hill Road North
When:  Monday, June 15, through Thursday, June 18, 8.a.m. - 3:30p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Right lane closure
Where: From Route 7 to 500 feet passed Route 7 
Why:  Manhole and sidewalk repairs
 
Tyco Road South
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Right lane closure
Where: From Route 7 to 400 feet before Route 7 
Why:  Manhole and sidewalk repairs
 
Tyco Road North
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Right lane closure
Where: From Route 7 to 500 feet passed Route 7 
Why:  Manhole and sidewalk repairs
 
Tysons Boulevard North
When:  Monday, June 15, through Thursday, June 18,  8.a.m. - 3:30 p.m., and Friday, June 19, 8 a.m. - 2 p.m.
What:  Right lane closure
Where: From Tysons Boulevard to Route 123
Why:  Underdrain installation
 
To view this alert on the Dulles Corridor Metrorail Project website, click here.
 
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.