Large Off-Site Fill Material, Concrete Deliveries for the
Week of April 18 - April 23
The following construction deliveries are scheduled Monday - Saturday, April 18 - April 23, in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below.
FILL MATERIAL
![]() WHEN: Between the hours of 7:30 a.m. to 4 p.m.
HOW: Trucks will travel from the Reston Site via Reston Parkway (Rt. 602), Dulles Toll Road (Rt. 267), Old Ox Road (Rt. 606) and Mercure Circle. Return trip will be Old Ox Road (Rt. 606), Dulles Toll Road (Rt. 267) and Reston Parkway (Rt. 602).
There will be a Loudoun County Sheriff's Office deputy parked at the project entrance to help maintain traffic flow and awareness of increased truck volume. Roads will be cleaned during operations by a sweeper truck.
CONCRETE
WHAT: Concrete delivery (12 trucks) for installation of Austin Sand Filter foundation.
WHEN: Between the hours of 7:30 a.m. and 11:30 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site.
<><><><><>
|