Materials Delivery Schedule for July 22 - 26

July 19, 2019
 
CONTACT:          Marcia McAllister
 T: 703-572-0506
 C: 571-730-9117
 Marcia.McAllister@dullesmetro.com
 
 
 
 
 
Materials Delivery Schedule for July 22 - 26
  
 
 
The following construction deliveries are scheduled for July 22 - 26 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below: 
 
 
 
 
WHAT: Car Hoist components delivery (1 truck) for installation in the Service and Inspection Building.
                 
WHEN: Monday and Thursday between the hours of 8 a.m. to 12 p.m.
 
HOW:   Trucks will travel from Youngstown, PA. West along Old Ox Rd/Rt. 606 to the project site.
 
--------------------------------------------------
 
WHAT: Bridge Crane components delivery (2 trucks) for installation in the Service and Inspection Building.
                 
 WHEN: Friday between the hours of 12 p.m. to 4 p.m.
 
 HOW:   Trucks will travel from Houston, TX. North along Old Ox Rd/Rt. 606 to the project site.
 
--------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.