Materials Delivery Schedule for Nov. 11 - 15
  
 
 
The following construction deliveries are scheduled for Nov. 11 - 15 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below: 
 
 
 
 
WHAT: Truck Repair Hoists delivery (1 truck) for installation in the Service and Inspection Building.
 
WHEN: Monday between the hours of 8 a.m. to 12 p.m.
 
HOW: Trucks will travel from Youngstown, PA. West along Route 606/Old Ox Road to the project site.
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.