Skip to main content
Silver Line on Track

Lane Closures Scheduled Along the Dulles Greenway, Dulles Toll Road and Sunset Hills Road June 15 - June 19

June 12, 2020
                                                                                
CONTACT: Marcia McAllister
                  T: 703-572-0506
                  C: 571-730-9117
                  marcia.mcallister@dullesmetro.com
 
Lane Closures Scheduled Along the Dulles Greenway, Dulles Toll Road and Sunset Hills Road 
June 15 - June 19
 
Lane closures are scheduled Monday, June 15, through Friday, June 19, along the Dulles Dulles Greenway, Dulles Toll Road and Sunset Hills Road near the future Reston Town Center Station to permit Silver Line Phase 2 crews to perform stormwater management work.  
 
See below for more detailed information.  
 
<><><> 
 
Dulles Greenway - East
When:  Monday, June 15 to Friday, June 19, 10 a.m. to 3:30 p.m.
What:   Single right lane closure
Where: From the ramp of Old Ox Road to Dulles Greenway 
Why:     Installation of attenuator and concrete barrier
 
Dulles Toll Road - East
When:  Monday, June 15 to Friday, June 19, 10 a.m. to 3:30 p.m.
What:   Work operation closure
Where: From the Dulles Toll Road ramp to 200 feet prior to the end of Dulles Toll Road ramp
Why:    Removal of concrete barrier and attenuator
 
When:  Monday, June 15 to Friday, June 19, 10 a.m. to 3:30 p.m.
What:   Partial exit ramp closure
Where: Near the Van Buren/Monroe Overpass
Why:     Equipment pickup or drop off
 
When:  Monday, June 15 to Friday, June 19, 9 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Reston Parkway Exit
Why:     Paving operation
 
Dulles Toll Road West
When:  Monday, June 15 to Friday, June 19, 10 a.m. to 3:30 p.m.
What:   Right shoulder closure
Where: Near Fairfax County Parkway
Why:     Installation of permanent fence
 
Sunset Hills Road East
When:  Monday, June 15 to Thursday, June 18, 9:30 a.m. to 3:30 p.m.,and Friday, June 19, 9:30 a.m. to 2:30 p.m.
What:   Single right lane closure
Where: From the Sunoco to Town Center Parkway
Why:     Installation of permanent fence
 
All work is weather dependent and subject to change.
 
Signs and barrels will be used to help direct traffic and minimize impacts.  Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.