Lane Closures Scheduled Along the Dulles Toll Road, Sunset Hills Road June 1 - June 5

May 29, 2020
                                                                                
CONTACT: Marcia McAllister
                  T: 703-572-0506
                  C: 571-730-9117
                  marcia.mcallister@dullesmetro.com
 
Lane Closures Scheduled Along the Dulles Toll Road, Sunset Hills Road June 1 - June 5
 
Lane closures are scheduled Monday, June 1, through Friday, June 5, along the Dulles Toll Road near the future Reston Town Center Station to permit Silver Line Phase 2 crews to perform stormwater management work.  
 
See below for more detailed information.  
 
<><><> 
 
Dulles Toll Road East
When:  Monday, June 1 to Friday, June 5, 9 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: From the Dulles Toll Road ramp to 200 feet prior to the end of Dulles Toll Road ramp
Why:     Paving operation
 
When:  Monday, June 1 to Friday, June 5, 10 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Near the Van Buren/Monroe Overpass
Why:     Paving operation
 
When:  Monday, June 1 to Friday, June 5, 10 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Reston Parkway Exit
Why:     Paving operation
 
Dulles Toll Road West
When:  Monday, June 1 to Friday, June 5, 10 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Near Fairfax County Parkway
Why:     Paving operation
 
Sunset Hills Road East
When:  Monday, June 1 to Thursday, June 4, 9:30 a.m. to 3:30 p.m.,and Friday, June 5, 9:30 a.m. to 2:30 p.m.
What:   Single right lane closure
Where: From the Sunoco to Town Center Parkway
Why:     Installation of permanent fence
 
All work is weather dependent and subject to change.
 
Signs and barrels will be used to help direct traffic and minimize impacts.  Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.