Lane Closures Scheduled Along the Dulles Toll Road, Sunset Hills Road June 8 - June 12
 
Lane closures are scheduled Monday, June 8, through Friday, June 12, along the Dulles Toll Road near the future Reston Town Center Station to permit Silver Line Phase 2 crews to perform stormwater management work.  
 
See below for more detailed information.  
 
<><><> 
 
Dulles Toll Road East
When:  Monday, June 8 to Friday, June 12, 10 a.m. to 3:30 p.m.
What:   Work operation closure
Where: From the Dulles Toll Road ramp to 200 feet prior to the end of Dulles Toll Road ramp
Why:     Removal of concrete barrier and attenuator
 
When:  Monday, June 8 to Friday, June 12, 10 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Near the Van Buren/Monroe Overpass
Why:     Equipment pickup or drop off
 
When:  Monday, June 8 to Friday, June 12, 10 a.m. to 3:30 p.m.
What:   Partial closure of exit ramp
Where: Reston Parkway Exit
Why:     Materials drop off
 
Dulles Toll Road West
When:  Monday, June 8 to Friday, June 12, 10 a.m. to 3:30 p.m.
What:   Right shoulder closure
Where: Near Fairfax County Parkway
Why:     Installation of permanent fence
 
Sunset Hills Road East
When:  Monday, June 8 to Thursday, June 11, 9:30 a.m. to 3:30 p.m.,and Friday, June 12, 9:30 a.m. to 2:30 p.m.
What:   Single right lane closure
Where: From the Sunoco to Town Center Parkway
Why:     Installation of permanent fence
 
All work is weather dependent and subject to change.
 
Signs and barrels will be used to help direct traffic and minimize impacts.  Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.