Silver Line on Track

Silver Line Testing to Start in Eastern Loudoun

July 24, 2019
 
CONTACT:  Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
Silver Line Testing to Start in Eastern Loudoun
 
(Photo courtesy of Nader Hamouda, Metropolitan Washington Airports Authority)
 
Test trains for Phase 2 of the Silver Line have rolled into Loudoun County.
 
The trains, now parked at the future Loudoun Gateway Metrorail Station along the Dulles Greenway just west of Dulles Airport, will be used for dynamic testing along a stretch of the rail corridor bordering Loudoun and Fairfax County. 
 
Working with the Washington Metropolitan Area Transit Authority (WMATA) staff, crews are ready to launch the third of several phases of this testing, a key component of preparations to completion of Phase 2.  
 
Dynamic Testing uses WMATA Trains to test components of the Automatic Trail Control System to verify the design and installation.
 
The Silver Line is being built by the Metropolitan Washington Airports Authority and will be turned over to WMATA when completed. Construction is being done by Capital Rail Constructors.
 
Airports Authority officials have targeted July of 2020 for construction completion.
 