Update on Realignment of Old Meadow Road  at Route 123 in Tysons Lane Shift Expected at End of September

 
 
September 18, 2020
                                                                            
 
Update on Realignment of Old Meadow Road 
at Route 123 in Tysons
Lane Shift Expected at End of September
 
As the realignment of Old Meadow Road with Capital One Tower Drive at Dolley Madison Boulevard (Route 123), near the Capital Beltway in Tysons, continues motorists can expect to see the travel lanes shift near the end of September as work moves from the south side of Old Meadow Road to the median area.
 
The Metropolitan Washington Airports Authority's Silver Line project is overseeing the work, which subcontractor W.M. Schlosser is performing. The Virginia Department of Transportation and Fairfax County requested the realignment to facilitate traffic crossing Route 123 from the Capital One complex to Old Meadow Road. The change is needed because of impacts caused by Silver Line construction near McLean Station.
 
Weather and differing site conditions have delayed the completion of the first phase of the work, which included sidewalk and pavement demolition as well as excavation and grading, and asphalt work. Crews have completed the installation of the new drainage infrastructure and are continuing with the new sidewalk and curb and gutter work. They will finish with the asphalt and landscaping along the south side of Old Meadow Road and the east side of Dolley Madison Boulevard to complete that part of the work.
 
When the next phase of work begins near the end of September, crews will finish the construction of a new median on Old Meadow Road at the intersection. The work will require a southward lane shift of eastbound Old Meadow Road.
 
<><><> 
 
 
                                                       Curb and gutter formwork underway along Old Meadow Road
Photo courtesy of Dulles Corridor Metrorail Project
 
Silver Line Phase 1 crew member places subbase material for sidewalk along Old Meadow Road
Photo courtesy of Dulles Corridor Metrorail Project
 
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 1 Dulles Corridor Metrorail Project construction-related issues: 800-685-5018. For general project information: www.dullesmetro.com or 703-572-0506.