December 23, 2016
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
|
Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for Dec. 26 - 30
![]() WHAT: Concrete delivery (30-35 trucks) for installation at the Service and Inspection Building Wheel Truing Pit Upper Slab (approximately 300 cubic yards). This will include a 47 Meter Pump Truck.
WHEN: Thursday and Friday between the hours of 7:00 a.m. to 10:00 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site.
<><><><><>
|