Aug. 25, 2017
Concrete Delivery Schedule for Aug. 28 - Sept. 1
![]() WHAT: Stone delivery (15 trucks) tof ballast material at the layup yard.
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
WHAT: Restraining Rail delivery (1 truck) to be installed in the yard lead track.
WHEN: Thursday between the hours of 7 a.m. to 1 p.m.
HOW: Trucks will travel from Allentown, PA, South on 15, East on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Precast Panel delivery (10 trucks) in 45 minute increments for installation at building TBD.
WHEN: Monday - Friday between the hours of 7 a.m. to 3 p.m.
HOW: Trucks will travel from Winchester, VA, East on Rte 7, South on 28, and West along Rte 606/Old Ox Rd to the project site, making the U-turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Turnout delivery (2 trucks) for installation in the yard lead track.
WHEN: Monday and Wednesday between the hours of 7 a.m. to 12 p.m.
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (15 trucks) for installation in the Maintenance of Way Track including a 39m pump truck.
WHEN: Wednesday and Thursday between the hours of 6 a.m. to 11 a.m.
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (11 trucks) for installation in the Transportation Polic Building Slab on Grade including a 36m pump truck.
WHEN: Thursday and Friday between the hours of 4 a.m. to 7 a.m.
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
<><><><><>
|