June 9, 2017
Concrete Delivery Schedule for June 12 - 16
![]() WHAT: Stone delivery (20 trucks) of ballast material at the layup yard.
WHEN: Tuesday - Friday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (10 trucks) for installation onsite for approach slabs, including a 36m pump truck.
WHEN: Wednesday between the hours of 8 a.m. to 1 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Precast Panel delivery (8 trucks) in 45 minute increments for installation at the Maintenance of Way Building.
WHEN: Monday - Friday between the hours of 7 a.m. to 2 p.m.
HOW: Trucks will travel from Winchester VA, East on rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Turnout delivery (2 - 3 trucks) for installation in the yard lead track.
WHEN: Tuesday, Thursday, and Friday between the hours of 7 a.m. to 12 p.m.
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Restraining Rail delivery (1 truck) to be installed in the yard lead track.
WHEN: Tuesday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Allentown, PA, South on 15, East on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Rebar delivery (1 truck) for installation in the Service & Inspection Building and Vehicle Storage Building.
WHEN: Monday and Wednesday between the hours of 6 a.m. - 10 a.m.
HOW: Trucks will travel from Trowbridge plant, West on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
WHAT: Roofing Insulation delivery (5 trucks) to be installed at the Service and Inspection Building.
WHEN: Monday between the hours of 7 a.m. - 5 p.m. Trucks will be staged off site, to allow the trucks to arrive one at a time.
HOW: Trucks will travel from Carlisle, PA, South on 15, East on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
WHAT: Structural Steel delivery (2 trucks) for installation at the Train Wash Facility.
WHEN: Tuesday and Thursday between the hours of 6 a.m. - 12 p.m.
HOW: Trucks will be coming from Tennessee, traveling North on Rte 606/ Old Ox Rd from US 50.
-------------------------------------------------------------------------------------------
<><><><><>
|