Nov. 2, 2018
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Marcia.McAllister@dullesmetro.com
Concrete Delivery Schedule for Nov. 5 - 9
The following construction deliveries are scheduled for Nov. 5 - 9 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
![]() <><><><><>
WHAT: Elevator Cab (1 truck) for delivery to Service and Inspection Building.
WHEN: Monday between the hours of 8 a.m. to 10 a.m.
HOW: Trucks will travel West along Route 606/Old Ox Road to the project site.
---------------------------------------------------
WHAT: Overhead Bridge Crane delivery (3 trucks) for delivery to Service and Inspection Building.
WHEN: Wednesday between the hours of 8 a.m. to 10 a.m.
HOW: Trucks will travel West along Route 606/Old Ox Road to the project site.
---------------------------------------------------
WHAT: Miscellaneous Equipment (Bearing Oven) delivery (1 truck).
WHEN: Wednesday between the hours of 8 a.m. to 10 a.m.
HOW: Trucks will travel West along Route 606/Old Ox Road to the project site.
---------------------------------------------------
WHAT: Overhead Bridge Crane delivery (3 trucks) for delivery to Service and Inspection Building.
WHEN: Friday between the hours of 8 a.m. to 10 a.m.
HOW: Trucks will travel West along Route 606/Old Ox Road to the project site.
<><><><><>
|