February 26, 2016 CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Important Lane and Ramp Closures for the Week of Feb. 28 - March 5
Dulles Toll Road (DTR) East
When: Sunday, Feb. 28 and Monday, Feb. 29, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What: Alternating right and left lane closures of varying length
Where: From mile marker 4.5 to 5.7 (between the Reston Parkway and Wiehle Avenue overpasses)
Why: Jack and bore operations
When: Sunday, Feb. 28 and Monday, Feb. 29 - 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What: Left lane closed
Where: From mile marker 2.5 to 4.5 (between the Centreville Road and Reston Parkway overpasses) Why: Jack and bore operations
Dulles Toll Road (DTR) West
When: Wednesday, March 2 - Saturday, March 5, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass) Why: Jack and bore operations
When: Wednesday, March 2 - Saturday, March 5, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 3.5 to 1.5 (between the Fairfax County Parkway overpass and Route 28) Why: Jack and bore operations
Dulles International Airport Access Highway (DIAAH) East
When: Sunday, Feb. 28 - Saturday, March 5, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 1.5 to 3.5 (Route 28 and the Fairfax County Parkway) Why: Construction entrance acceleration/deceleration lane
When: Monday, Feb. 29 - Saturday, March 5, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 3.7 to 5.7 (from Monroe Street overpass to the Reston Parkway overpass) Why: Construction entrance acceleration/deceleration lane
When: Sunday, Feb. 28 - Saturday, March 5, 9 p.m. to 5 a.m.
What: Eastbound lane reductions begin at 9 p.m. Eastbound full lane closures begin at 10 p.m. Road reopens at 5 a.m. Follow detour.
Where: From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass) Why: Installation of a concrete span across the eastbound DIAAH.
Dulles International Airport Access Highway (DIAAH) West
When: Sunday, Feb. 28 - Friday, March 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 3.5 to 1.5 (between the Fairfax County Parkway overpass and Route 28) Why: Construction entrance acceleration/deceleration lane When: Sunday, Feb. 28 - Friday, March 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass) Why: Construction entrance acceleration/deceleration lane
Dulles Greenway East
When: Monday, Feb. 29 - Thursday, March 4, 10 a.m. to 5 p.m.
What: Alternating right and left lane closures of varying lengths
Where: Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur Why: Road work
When: Saturday, Feb. 27, 10 a.m. to 5 p.m.
What: Left shoulder closure
Where: Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza) Why: Road work
Dulles Greenway West
When: Monday, Feb. 29 - Friday, March 4, 6 a.m. to 3 p.m.
What: Alternating right and left lane closures of varying lengths
Where: Between mile marker 12.0 and 7.6 (from 3/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur Why: Road work
When: Saturday, Feb. 27, 6 a.m. to 5 p.m.
What: Left lane
Where: Between mile marker 12.0 and 7.6 (from 2/10 mile before the mainline toll plaza to Broadlands Boulevard) Why: Road work
Autopilot Drive
When: Monday, Feb. 29 - Wednesday, March 2, 5, 9 a.m. to 2 p.m.
What: Left lane closed
Where: Westbound Aviation Drive at the intersection of Autopilot Drive Why: Fiber line
When: Sunday, Feb. 28 - Saturday, March 5, 9 p.m. to 5 a.m.
What: Northbound lanes closed; northbound traffic diverted to one southbound lane.
Where: Autopilot Drive from Rudder Road to Materials Road Why: Superstructures work
Sunset Hills Road East
When: Sunday, Feb. 28 - Tuesday, March 1, 9:30 a.m. to 3:30 p.m.
What: Right lane closed
Where: Between Fairfax County Parkway and Reston Parkway Why: Excavation
Sunrise Valley Drive West
When: Monday, Feb. 29 - Thursday, March 3, 8:30 a.m. to 3:30 p.m., and Friday, March 4, 8:30 a.m. to 12 p.m.
What: Right lane closed
Where: Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard Why: Construction Deliveries
Old Ox Road (Route 606) When: Monday, Feb. 29 - Friday, March 4, 1:45 p.m. to 2:30 p.m.
What: Five-minute road closures in both directions
Where: From Commerce Center Court to Mercure Circle Why: Rock blasting
<><><><><>
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|