January 11, 2019
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Important Lane and Ramp Closures for the
Week of Jan. 13 - Jan. 19
Dulles Corridor Metrorail Project crews continue construction activities for the Metrorail Silver Line Phase 2 that require lane, shoulder, and road closures and detours at locations along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Autopilot Drive, Herndon Parkway, Edmund Halley Drive, Sunrise Valley Drive, Sunset Hills Road, Lockridge Road, and Moran Road during the week of Jan. 13 - Jan. 19, 2019. In addition, there will be lane closures along the Phase 1 alignment as listed below.
See below for more specific dates, times and details and remember that all work is weather permitting.
PLEASE USE CAUTION and remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
<><><>
Dulles Toll Road East
When: Monday, Jan. 14 to Friday, Jan. 17, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m. Saturday, Jan. 18, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where:From mile marker 1.3 to 5.2 (from just west of the Route 28 overpass to the Reston Parkway overpass)
Why: Civil work
When: Wednesday, Jan. 16, through Friday, Jan. 18, 9:30 a.m. - 3:30 p.m.
What: Left lane closure
Where: From 500 feet west of Reston Parkway Overpass (MM 5.7) to 300 feet before Wiehle Avenue Overpass (MM 6.0)
Why: Removal of crossover gate
Dulles Toll Road West
When: Monday, Jan. 14 to Friday, Jan. 17, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
Saturday, Jan. 18, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where:From mile marker 5.7 to 1.5 (between the Route 28 and Reston Parkway overpasses)
Why: Civil work
When: Tuesday, Jan. 15 to Thursday, Jan. 16, 10 p.m. to 5 a.m.
What: Triple left lane closure with up to 20-minute stoppages
Where:From mile marker 5.1 to 3.5 (from Reston Parkway to the west end of Herndon Station
Why: Civil work
When: Tuesday, Jan. 15, through Friday, Jan. 18, 9:30 a.m. - 3:30 p.m.
What: Left lane closure
Where: From 300 feet west of Wiehle Avenue Overpass (MM 6.0) to 400 feet of Reston Parkway Overpass (MM 5.6)
Why: Removal of crossover gate
When: Monday, Jan. 14, through Thursday, Jan. 17, 9:30 a.m. - 3:30 p.m.
What: Left lane closure
Where: From 200 feet west of Hunter Mill Road Bridge (MM 7.5) to the W&OD Trail (MM 6.8)
Why: Removal of crossover gate
Dulles International Airport Access Highway (DIAAH) East
When: Monday, Jan. 14 to Friday, Jan. 17, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m. Saturday, Jan. 18, 5 a.m. to 2 p.m.
What: Alternating right and left lane closures of varying lengths
Where:From mile marker 0.0 to 5.7 (from the Aviation Drive overpass to 5/10 mile after the Reston Parkway overpass)
Why: Civil work
When: Friday, Jan. 17, 10 p.m. to Saturday, Jan. 18, 5 p.m.
What: Detour
Where: From mile marker 2.7 to 4.0 (from the Centreville Road overpass to 2/10 mile west of Fairfax County Parkway)
Why: Herndon pedestrian bridge utilities
Dulles International Airport Access Highway (DIAAH) West
When: Monday, Jan. 14 to Friday, Jan. 17, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Saturday, Jan. 18, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 7.3 to 0.0 (from approximately 7/10 mile west of Hunter Mill Road to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal)
Why: Civil and Dulles Airport Metrorail Station work will be taking place within the closures
When: Tuesday, Jan. 15, through Friday, Jan. 18, 9:30 a.m. - 3:30 p.m.
What: Right lane closure
Where: From 300 feet west of Wiehle Avenue Overpass (MM 6.0) to 400 feet of Reston Parkway Overpass (MM 5.6)
Why: Removal of crossover gate
When: Monday, Jan. 14, through Thursday, Jan. 17, 9:30 a.m. - 3:30 p.m.
What: Right lane closure
Where: From the Hunter Mill Road Bridge on ramp (MM 7.5) to 200 feet of the W&OD Trail (MM 6.8)
Why: Removal of crossover gate
Dulles Greenway East
When: Monday, Jan. 14 to Friday, Jan. 17, 10 a.m. to 6 p.m., 6 p.m. to 5 a.m.
Saturday, Jan. 18, 6 a.m. to 6 p.m.
What: Alternating left and right lane closures of varying lengths
Where: From mile marker 7.6 to 11.5 (from approximately 2/10 mile west of Waxpool Road to the Moran Road exit)
Why: Civil work
Dulles Greenway West
When: Monday, Jan. 14 to Friday, Jan. 17, 6 a.m. to 3 p.m., 8 p.m. to 6 a.m.
Saturday, Jan. 18, 6 a.m. to 6 p.m.
What: Alternating left and right lane closures of varying lengths
Where:From mile marker 11.5 to 7.6 (from the Moran Road exit to Broadlands Boulevard overpass)
Why: Civil work
When: Thursday, Jan. 17 to Friday, Jan. 18, 10 p.m. to 5 a.m.
What: Double left lane closure
Where: From mile marker 10.0 to 8.5 (from 2/10 mile east of Loudoun County Parkway to the Ashburn Village Blvd overpass)
Why: OH Utility
Sunset Hills Road East
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Alternating right and left lane closures
Where: From 400 feet west of Town Center Pkwy to Bechtel Building Entrance
Why: Civil work
Herndon Parkway East
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why: Equipment mobilization
Sunrise Valley Drive West
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Dulles Technology Drive to Dulles Station Blvd
Why: Civil Work
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Thunder Chase Drive to Millburn Lane
Why: Civil Work
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Right lane closed
Where: From Reston Pkwy to 200' West of Edmund Halley Dr.
Why: Civil Work
Edmund Halley Drive North and South
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Right shoulder closed
Where: From Sunrise Valley Drive to 1000 feet north of Sunrise Valley Drive
Why: Civil utility work
Moran Road South
When: Monday, Jan. 14 to Thursday, Jan. 16, 9:30 a.m. to 3:30 p.m.
Friday, Jan. 17, 9:30 a.m. to 12 p.m.
What: Alternating left and right lane closures
Where: From Moran Road to Old Ox Road
Why: Civil work
I-66 East
When: Sunday, Jan. 13 - Thursday, Jan. 17, 9:30 p.m. - 5 a.m.
What: Inside left lane and shoulder closure
Where: From Williamsburg Boulevard to Haycock Road Bridge
Why: Cleaning and installing pipe repair bands
Dulles Connector Road - East
When: Sunday, Jan. 13 - Thursday, Jan. 17, 9:30 p.m. - 5 a.m.
What: Inside left lane and shoulder closure on a four-lane road
Where: From Chain Bridge Road to I-66
Why: Cleaning and storm drain work
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|