Large Off-Site Fill Material, Concrete Deliveries for the Week of May 23 - May 28
The following construction deliveries are scheduled May 23 - May 28 (Monday - Saturday), in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below.
FILL MATERIAL
![]() WHEN: Between the hours of 7 a.m. and 4 p.m.
HOW: Trucks will travel from the Reston Site via Reston Parkway (Rt. 602), Dulles Toll Road (Rt. 267), Old Ox Road (Rt. 606) and Mercure Circle. Return trip will be Old Ox Road (Rt. 606), Dulles Toll Road (Rt. 267) and Reston Parkway (Rt. 602). Roads will be cleaned during import fill operations by a sweeper truck.
CONCRETE
WHAT: Concrete delivery (24 trucks) and concrete pump truck for installation of Service and Inspection Building's Mud Mat.
WHEN: Tuesday, May 24 between the hours of 6 a.m. and 12 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site.
WHAT: Concrete delivery (12 trucks) and concrete pump truck for installation of Austin Sand Filter Walls.
WHEN: Friday, May 27, between the hours of 6 a.m. and 11 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
<><><><><>
|