July 12, 2019
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Marcia.McAllister@dullesmetro.com
Materials Delivery Schedule for July 15 - 19
The following construction deliveries are scheduled for July 15 - 19 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
![]() WHAT: Car Hoist components delivery (1 truck) for installation in the Service and Inspection Building.
WHEN: Thursday between the hours of 8 a.m. to 12 p.m.
HOW: Trucks will travel from Youngstown, PA. West along Old Ox Rd/Rt. 606 to the project site.
--------------------------------------------------
WHAT: Bridge Crane components delivery (1 truck) for installation in the Service and Inspection Building.
WHEN: Thursday between the hours of 8 a.m. to 3 p.m.
HOW: Trucks will travel from Houston, TX. North along Old Ox Rd/Rt. 606 to the project site.
--------------------------------------------------
WHAT: Bridge Crane components delivery (2 trucks) for installation in the Service and Inspection Building.
WHEN: Friday between the hours of 8 a.m. to 3 p.m.
HOW: Trucks will travel from Houston, TX. North along Old Ox Rd/Rt. 606 to the project site.
--------------------------------------------------
WHAT: Bridge Crane components delivery (5 trucks) for installation in the Service and Inspection Building.
WHEN: Wednesday between the hours of 8 a.m. to 3 p.m.
HOW: Trucks will travel from Houston, TX. North along Old Ox Rd/Rt. 606 to the project site.
--------------------------------------------------
<><><><><>
|