August 26, 2016
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Important Lane and Ramp Closures for the
Week of August 28 - September 3
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane, shoulder, road and ramp closures will occur along the Dulles Toll Road, Dulles International Airport Access Highway, Autopilot Drive, Rudder Road, Dulles Greenway, Route 28, Centreville Road, Sunrise Valley Drive and Sunset Hills Road during the week of August 28 - September 3.
Construction activities on Autopilot Drive and Rudder Road at Dulles International Airport will continue overnight from August 29 through September 1 between 9 p.m. and 5 a.m. with various lane closures and detours occurring each night. Drivers should remain alert, pay attention to all signs, and follow police and flagger instructions. All cargo and car rental facilities will be accessible. All work is weather permitting.
See below for more detailed information.
<><><>
Dulles Toll Road East
When: Monday, August 29 - Thursday, September 1, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m. Friday, September 2, 10 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass) Why: Jack and bore, duct bank work
When: Monday, August 29 - Thursday, September 1, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m. Friday, September 2, 10 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe Street overpass to the Reston Parkway overpass) Why: Jack and bore operations
Dulles Toll Road West
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m. Friday, September 2, 9:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass) Why: Jack and bore operations
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m. Friday, September 2, 9:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 3.5 to 1.5 (from 1/10 mile before the Monroe/Van Buren Street overpass to 3/10 mile before the Route 28 overpass) Why: Jack and bore operations
Dulles International Airport Access Highway (DIAAH) East
When: Monday, August 29 - Thursday, September 1, 10 p.m. to 5 a.m. What: Full closure begins at 10 p.m.; follow detour. Road reopens at 5 a.m. Where: From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass) Why: Installation of a concrete span across the eastbound DIAAH
When: Monday, August 29 - Thursday, September 1, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m. Friday, September 2, 8:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 0.0 to 2.3 (from Saarinen Circle to 2/10 mile before the Centreville Road overpass) Why: Construction entrance acceleration/deceleration lane
When: Monday, August 29 - Thursday, September 1, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m. Friday, September 2, 8:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 3.3 to 5.4 (from 1/10 mile before the Monroe Street overpass to 2/10 mile past the Reston Parkway overpass) Why: Construction entrance acceleration/deceleration lane
Dulles International Airport Access Highway (DIAAH) West
When: Monday, August 29 - Thursday, September 1, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m. Friday, September 2, 7:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass) Why: Road work
When: Monday, August 29 - Thursday, September 1, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m. Friday, September 2, 7:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 3.3 to 0.3 (from 1/10 mile past the Monroe Street overpass to 2/10 milast the Rudder Road overpass) Why: Duct bank work
When: Monday, August 29 - Thursday, September 1, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m. Friday, September 2, 7:30 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1) Why: Construction entrance acceleration/deceleration lane
When: Monday, August 29 - Thursday, September 1, 10 p.m. to 5 a.m. What: Two left lanes closed, right lane diverted around work area Where: From mile marker 0.3 to Saarinen Circle (from 2/10 mile past the Rudder Road overpass to Saarinen Circle near Garage 1), traffic will be diverted around work area. Why: Installation of a concrete span across the westbound DIAAH.
Autopilot Drive North and South
When: Monday, August 29 - Thursday, September 1, 9 p.m. to 4 a.m. What: Full closure of northbound and southbound lanes OR single lane closures will occur Where: From Rudder Road to 700 feet north of Rudder Road (near the Hertz car rental facility). Follow detour. Why: Aerial guideway construction
Rudder Road East and West
When: Monday, August 29 - Thursday, September 1, 9 p.m. to 5 a.m. What: Eastbound and westbound lanes closed Where: From Autopilot Drive to Air Freight Lane. Follow detour to Package Court. Why: Aerial guideway construction
Dulles Greenway East
When: Monday, August 29 - Thursday, September 1, 10 a.m. to 6 p.m. and 6 p.m. to 10 p.m. Friday, September 2, 10 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur Why: Road work
When: Monday, August 29 - Thursday, September 1, 10 p.m. to 5 a.m. What: Two right lanes closed Where: From mile marker 11.0 to 12.0 (from the Old Ox Road overpass to 4/10 mile before the mainline toll plaza) Why: Installation of a concrete span across the eastbound Dulles Greenway
Dulles Greenway West
When: Monday, August 29 - Thursday, September 1, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m. Friday, September 2, 6 a.m. to noon What: Alternating right and left lane closures of varying lengths Where: Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur Why: Road work
When: Monday, August 29 - Thursday, September 1, 3 a.m. to 3 p.m. Friday, September 2, 3 a.m. to noon What: Two left lanes closed Where: From mile marker 11.0 to 10.5 (from the Old Ox Road overpass to the Broad Run bridge) Why: Bridge work
Route 28 South
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3:30 p.m. Friday, September 2, 9:30 a.m. to noon What: Right lane closure Where: From the ramp to the eastbound Dulles Toll Road to the ramp to Frying Pan Road Why: Duct bank
Centreville Road North and South
When: Monday, August 29 - Thursday, September 1, 10 p.m. to 5 a.m. What: Right lane closed Where: Between Woodland Park and Parcher Avenue Why: Bridge work
Sunset Hills Road East
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3:30 p.m. Friday, September 2, 9:30 a.m. to noon What: Right lane closed Where: Between the Fairfax County Parkway and Reston Parkway Why: Excavation
Sunrise Valley Drive East
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3:30 p.m. Friday, September 2, 9:30 a.m. to noon What: Right lane narrows Where: From 700 feet west of Dulles Station Boulevard to Dulles Station Boulevard Why: Water line installation
Sunrise Valley Drive West
When: Monday, August 29 - Thursday, September 1, 9:30 a.m. to 3:30 p.m. Friday, September 2, 9:30 a.m. to noon What: Right lane closed Where: Between Thunder Chase Drive and Hitchcock Drive Why: Utility location <><><><><>
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|