June 13, 2017
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Construction Activities Along the Dulles Access Highway and
Dulles Toll Road Near Herndon and
Reston Town Center Metrorail Stations
Friday, June 16 at 9 p.m. to Tuesday, June 20 at 5 a.m.
Construction will detour eastbound traffic on the Dulles International Airport Access Highway (DIAAH) to the eastbound Dulles Toll Road (DTR) overnight between the Fairfax County Parkway overpass at the Reston Parkway overpass on or about Friday, June 16 at 9 p.m. through Monday, June 19 at 5 a.m.
The detour will allow Dulles Corridor Metrorail Project crews to continue construction of the Reston Town Center Metrorail Station in the median of the Dulles Access Highway. All work is weather dependent and subject to change.
Friday, June 16, 9 p.m. to Monday, June 19, 5 a.m. (See Figure 1)
Sunday, June 18, 7 p.m. to Monday, June 19, 5 a.m.
During the overnight hours on Sunday night, June 18 and Monday night, June 19, double lane closures will occur on the westbound DTR while crews conduct striping operations.
Monday, June 19, 10 p.m. to Tuesday, June 20, 5 a.m. (if needed)
<><><><><>
A 24/7 emergency hotline is available for Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|