Daily Lane Closures Remain Along Eastbound, Dulles Connector Road, June 20 – June 24

 
 
June 17, 2022
 
CONTACT: Marcia McAllister
                  T: 703-572-0506
                  C: 571-730-9117
                  marcia.mcallister@dullesmetro.com
 
Daily Lane Closures Remain Along Eastbound, Dulles Connector Road, June 20 – June 24
 
 
 
Daily lane closures continue along eastbound DCR for Monday, June 20, to Friday, June 24 permitting Dulles Corridor Metrorail Project crews to relocate concrete barriers and cones along the left shoulder. 
 
The Dulles Corridor Metrorail Project is making these enhancements at the request of the Virginia Department of Transportation as part of the Silver Line Phase 1 project. Please see detailed information below.
 
Dulles Connector Road (Route 267) – EAST
 
When: Monday, June 20, to Friday, June 24, 9:30 p.m. – 5 a.m.
What:  Single left lane closure
Where: From Chain Bridge Road to 2400 feet after Magarity Road
Why:  Relocate concrete barriers and cones
 
When: Monday, June 20, to Friday, June 24, 9:30 p.m. – 5 a.m.
What:  Single left lane closure
Where: From 1500 feet before Dolley Madison Boulevard to 1400 feet before Idylwood Road
Why:  Relocate concrete barriers and cones
 
When: Monday, June 20, to Friday, June 24, 9:30 p.m. – 5 a.m.
What:  Right shoulder taper
Where: From Magarity Road to 2700 feet after Magarity Road
Why:  Relocate concrete barriers and cones
 
 
All work is weather dependent and subject to change.
Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
 
 
<><><><><>
 
For general project information: www.dullesmetro.com or 703-572-0506.