Lane Closures Set for Dulles Toll Road, May 3 - May 7
Lane closures are scheduled Monday, May 3, through Friday, May 7, along the Dulles Toll Road near the future Herndon Station to permit Silver Line Phase 2 crews to perform stormwater management work. See below for more specific dates, times and details and remember that all work is weather permitting.
<><><>
Dulles Toll Road East to Route 28 South Ramp
When: Monday, May 3 to Friday, May 7, 10 a.m. - 3:30 p.m.
What: Partial exit ramp closure
Where: From Reston Parkway ramp to 200 Feet before Reston Parkway ramp
Why: Equipment drop off and punchlist work
Dulles Toll Road East
When: Monday, May 3 to Friday, May 7, 10 a.m. - 3:30 p.m.
What: Partial exit ramp closure
Where: Route 28 North ramp from Dulles Access Road to Route 28 exit ramp
Why: Equipment drop off and punchlist work