Airports Authority, DIAAH Pavement Rehabilitation Westbound from east of Centreville Road to east of Spring Hill Road. September 28 – December 27, 2022.

DIAAH Pavement Rehabilitation

Westbound from east of Centreville Road to east of Spring Hill Road. September 28 – December 27, 2022.

Beginning on Wednesday, September 28, and ending on or about Tuesday, December 27, paving work will be performed along the westbound lanes from Centreville Road to Spring Hill Road. The work will also include shoulders and a slip ramp within the project limits.

Work will be between the hours of 8:00PM until 6:00AM. Active construction may take place seven days a week. Please use extreme caution when traveling through this area.