![]() WHAT: Stone delivery (20-30 trucks) of sub ballast material at the layup yard.
WHEN: Monday – Friday between the hours of 7:30 a.m. to 5:00 p.m. HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site. -----------------------------------------------------------------------------------------
WHAT: Switch ties delivery (5 trucks) for installation in the layup yard.
WHEN: Tuesday between the hours of 7:00 a.m. to 2:00 p.m. HOW: Trucks will travel from Delaware, West on 267, South on Rte 606/ Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite. -----------------------------------------------------------------------------------------
WHAT: Switch Steel Parts delivery (3 Trucks) for installation in the layup yard.
WHEN: Thursday between the hours of 8:00 a.m. to 12:00 p.m. HOW: Trucks will travel from Delaware, traveling West on Old Ox Rd/Rt. 606 to the project site. -----------------------------------------------------------------------------------------
WHAT: Rail delivery (3 95’ Trucks including 2-4 escorts) for installation in the layup
yard. WHEN: Monday - Friday between the hours of 8:00 a.m. to 10:00 a.m. HOW: Trucks will travel from Delaware, traveling West on Old Ox Rd/Rt. 606 to the project site. <><><><><>
|