July 21, 2017
Concrete Delivery Schedule for July 24 - 28
![]() WHAT: Stone delivery (20 trucks) of ballast material at the layup yard.
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (20 trucks) for installation at the Service and Inspection Building Slab on Grade, sequence 2, including a 36m Z boom truck.
WHEN: Tuesday and Wednesday between the hours of 3 a.m. to 8 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Restraining Rail delivery (1 truck) to be installed in the yard lead track.
WHEN: Thursday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Allentown, PA, South on 15, East on 267, South on Old Ox Rd/Rt. 606, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Precast Panel delivery (16 trucks) in 45 minute increments for installation at the Maintenance of Way Building.
WHEN: Thursday between the hours of 7 a.m. to 2 p.m.
HOW: Trucks will travel from Winchester, VA, East on Rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Concrete Ties delivery (6 trucks) for installation in the yard lead track.
WHEN: Monday - Friday between the hours of 7 a.m. to 12 p.m.
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Turnout delivery (2 - 3 trucks) for installation in the yard lead track.
WHEN: Tuesday - Friday between the hours of 7 a.m. to 12 p.m.
HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
WHAT: Rebar delivery (1 truck) for installation in the Maintenance of Way Building and Transportation and Police Building.
WHEN: Tuesday between the hours of 6 a.m. to 10 a.m.
HOW: Trucks will travel from the Trowbridge plant, West on Old Ox Rd/Rt. 606, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
WHAT: Skylight delivery (1 truck) to be installed at the Service and Inspection Building.
WHEN: Thursday between the hours of 7 a.m. to 5 pm.
HOW: Trucks will travel from Georgia, North on 95, West on 267, South on Old Ox Rd/Rt. 606, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
WHAT: Roofing delivery (6 trucks) to be installed at the Maintenance of Way Building.
WHEN: Monday and Tuesday between the hours of 7 a.m. to 5 pm. Trucks will be staged off site to allow the trucks to arrive one at a time.
HOW: Trucks will travel from Carlisle, PA, South on 15, East on 267, South on Old Ox Rd/Rt. 606, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
<><><><><>
|