October 25, 2018
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Lane Closures Planned Along Route 7, I-66 and Route 123, Oct. 28 - Nov. 2
Lane closures are planned Sunday, Oct. 28, through Friday, Nov. 2, along eastbound Route 7, westbound I-66 and northbound Route 123 near the Silver Line Phase 1 alignment to permit construction crews to perform pipe repairs and underdrain work.
See below for more detailed information.
Route 7 East
When: Sunday, Oct. 28 - Friday, Nov.2, 9:30 p.m. - 5 a.m.
What: Left and right lane closures
Where: From Route 267 ramp to Chain Bridge Road
Why: Installing pipe repair bands and liners
Route 7 East
When: Monday, Oct. 29 - Thursday, Nov.1, 9:30 a.m. - 3:30 p.m.
Friday, Nov. 2, 9 a.m. - 1 p.m.
What: Right lane closure
Where: From 100 feet before Route 267 exit ramp to Marshalls Drive
Why: Survey for underdrain
When: Sunday, Oct. 28 - Friday, Nov.2, 9:30 p.m. - 5 a.m.
What: Left lane closure
Where: From Williamsburg Boulevard to Route 267 (Dulles Connector Road) north ramp
Why: Installing repair bands and liners
Route 123 North
When: Monday, Oct. 29 - Thursday, Nov.1, 9:30 a.m. - 3:30 p.m.
Friday, Nov. 2, 9 a.m. - 1 p.m.
What: Left turn lane closure
Where: From just south of Old Meadow Road to Colshire Drive
Why: Survey for underdrain
All work is weather dependent and subject to change.
Signs and barrels will be used to help direct traffic and minimize impacts. Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
<><><><><>
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.
|