June 19, 2020
CONTACT: Marcia McAllister
T: 703-572-0506
C: 571-730-9117
Lane Closures Remain Along Route 7, Spring Hill Road, Tyco Road and Tysons Boulevard June 22 - June 26
Dulles Corridor Metrorail Project crews will close the eastbound and westbound turn lanes along Route 7, the southbound and northbound lanes of Spring Hill Road, the southbound and northbound lanes of Tyco Road and Tysons Boulevard Monday, June 22, through Friday, June 26. Crews will be making sidewalk and other repairs near the Silver Line Phase 1 alignment. Please see detailed information below
Route 7 - East
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Left turn lane closure
Where: From 300 feet before Westwood Center Drive to Route 7
Why: Manhole and sidewalk repairs
Route 7 - West
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Left lane closure
Where: From 300 feet before Westpark Road to 400 feet after Westpark Road
Why: Underdrain Installation
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From 300 feet before Tyco Road to 300 feet Dulles Toll Road exit ramp
Why: Manhole and sidewalk repairs
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3:30 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From 600 feet before Spring Hill Road to 300 feet after Spring Hill Road
Why: Manhole and sidewalk repairs
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3:30 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From 500 feet before Route 7 to Route 7
Why: Manhole and sidewalk repairs
Spring Hill Road - Northbound
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3:30 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From Route 7 to 500 feet passed Route 7
Why: Manhole and sidewalk repairs
Tyco Road - Southbound
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From Route 7 to 400 feet before Route 7
Why: Manhole and sidewalk repairs
Tyco Road - Northbound
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From Route 7 to 500 feet passed Route 7
Why: Manhole and sidewalk repairs
Tysons Boulevard - Eastbound
When: Monday, June 22, through Thursday, June 25, 8.a.m. - 3:30 p.m., and Friday, June 26, 8 a.m. - 2 p.m.
What: Right lane closure
Where: From Galleria Drive to Route 123
Why: Underdrain installation
PLEASE DRIVE CAREFULLY! Drivers should exercise caution when driving in this area and remain alert for directional signs.
<><><><><>
A 24/7 emergency hotline is available for Phase 1 Dulles Corridor Metrorail Project construction-related issues: 800-685-5018. For general project information: www.dullesmetro.com or 703-572-0506.
|